Quote #:

Q-000001

Quote Date:

October 08, 2025

Expiration Date:

November 07, 2025

PROJECT QUOTATION REPORT

Quotation For:

N/A

N/A

Structure Layout Drawing

SILVER STEEL MILLS

silversteelmills.com | +92 324 9500004 | Lahore, Pakistan

PROJECT QUOTATION REPORT

Estimated Costs Breakdown

Item Value
Main Frame Steel Weight (kg): 0 kg
Secondary Steel Weight (Purlin + Girt) (kg): 0 kg
Total Cladding Area (sq ft): 0 sq ft
Cladding Details: N/A
Cladding Material Cost (PKR): PKR 0
Accessories Cost (PKR): PKR 0
Total Material Cost (PKR) (Frame + Secondary Steel + Cladding + Accessories): PKR 0
Erection/Labor Cost (PKR): PKR 0
**Total Project Cost (PKR):** PKR 0

This estimation is based on the provided rates and standard PEB engineering principles. Actual rates and material requirements may vary based on your project and market fluctuations.

SILVER STEEL MILLS

silversteelmills.com | +92 324 9500004 | Lahore, Pakistan

PROJECT QUOTATION REPORT

Terms and Conditions

1. Design Codes and Loads

All structural design loads and engineering codes are based on current construction regulations, as per Section 1. Any changes requested by the client will require a revised quotation, including updated costs and timelines.

2. Drawings and Approvals

This quotation and the latest drawings supersede all previous documents, discussions, or revisions. Any changes in parameters during or after drawing approval will result in revised costs and a new delivery schedule, subject to both technical and commercial approval.

3. Material Supply & Delivery

Materials will be delivered promptly upon 100% advance payment. Fabrication can be managed at both the factory and the site, depending on project needs. Storage space for delivered materials must be provided by the client.

4. Payment Terms

A) Material Supply

100% Advance Payment upon order confirmation.

B) Erection Work (Step-by-Step Payment Schedule)

Stage Payment Description
1 40% Upon confirmation of erection order
2 30% After fabrication of main frames
3 20% After erection of roofing, cladding, and structural works
4 10% Upon final completion and client approval